EVPL South Shore Outlook (upcoming work details)

Scheduled Activities During Week of December 08January 09
 
Victoria Pedestrian Overpass area:
Work on the Victoria Drive Pedestrian Overpass continues (Activity 2).  This will be noisy daytime work that will continue until mid-January 2015.  Works to be completed this year include installation of the cladding, glazing, electrical components and landscaping.  It is currently anticipated the elevator installation and commissioning will be the only works to be completed in 2015.  Daytime work is scheduled for Saturdays. There is no planned evening work.
 
Rogers/Vanterm
The connector road from Stewart Street to Rogers Street has been paved.  Lining marking will be completed as soon as possible (weather permitting).
Commissioner/McGill
Installation of the traffic light hardware is scheduled for the week of December 8th. Traffic lights will be operational after commissioning in the week of December 15th.